3/26/2016

Truck 2 - This week your apparatus finished on the main assembly line and was staged to finish assembly in an offline area. In the next few days, your apparatus should be released to alignment and initial testing. Next week your apparatus is scheduled to finish initial testing and may be back on the line where reflective striping and/or remaining content is added.

Truck 3

This week your apparatus was nearing completion on the final assembly line where a majority of the components were installed. Next week your apparatus is scheduled to be released to alignment and initial pump testing.

Truck 4

This week your apparatus was nearing completion on the final assembly line where a majority of the components were installed. Next week your apparatus is scheduled to be released to alignment and initial pump testing.

Truck 5

This week your apparatus was nearing completion on the final assembly line where a majority of the components were installed. Next week your apparatus is scheduled to be released to alignment and initial pump testing.

Truck 6

This week your apparatus continued on the final assembly line where a majority of the components were installed. Next week your apparatus is scheduled to be released to alignment and initial pump testing.

Truck 7

Early this week the body and water tank were merged with the chassis on the main assembly line where a majority of the components will be added. Next week your apparatus should finish on the main assembly line and is scheduled to be released to alignment and initial testing.

Truck 8

Early this week the body and water tank were merged with the chassis on the main assembly line where a majority of the components will be added. Next week your apparatus should finish on the main assembly line and is scheduled to be released to alignment and initial testing.

Truck 9

This week the body and water tank were merged with the chassis on the main assembly line where a majority of the components will be added. Next week your apparatus should be nearing completion on the main assembly line.

Truck 10

Early this week the cab finished on the cab line and was merged with the chassis along with the pump house. It also began the final assembly line where the body was merged with the chassis. Next week the tank should be added and your apparatus should continue on the final assembly line.

3/19/2016

Truck 2

This week your apparatus was nearing completion on the final assembly line where a majority of the components were installed. Next week your apparatus is scheduled to be released to alignment and initial pump testing.

Truck 3

Early this week the body and water tank were merged with the chassis on the main assembly line where a majority of the components will be added. Next week your apparatus should finish on the main assembly line and is scheduled to be released to alignment and initial testing.

Truck 4

Early this week the cab was merged with chassis and pump house. At the time of this report the body and water tank were merged with the chassis on the main assembly line where a majority of content will be added. Next week your apparatus should continue on the main assembly line.

Truck 5

Early this week the body and water tank were merged with the chassis on the main assembly line where a majority of the components will be added. Next week your apparatus should finish on the main assembly line and is scheduled to be released to alignment and initial testing.

Truck 6

Early this week the cab was merged with chassis and pump house. At the time of this report the body and water tank were merged with the chassis on the main assembly line where a majority of content will be added. Next week your apparatus should continue on the main assembly line.

Truck 7

This week the cab finished on the cab line and has been merged with the chassis along with the pump house. The body finished in paint and on the body line where harnessing and trim are added. Next week the chassis is scheduled to begin on the main assembly line where the body and water tank should be merged with the chassis.

Truck 8

This week the cab finished on the cab line and has been merged with the chassis along with the pump house. The body finished in paint and on the body line where harnessing and trim are added. Next week the chassis is scheduled to begin on the main assembly line where the body and water tank should be merged with the chassis.

Truck 9

This week the cab finished on the cab line and has been merged with the chassis along with the pump house. The body was nearing completion in paint. Next week the chassis is scheduled to begin on the main assembly line where the body (after harnessing and trim are added) and water tank may be merged with the chassis.

Truck 10

This week the cab began on the cab line where cab related content is added. The chassis has been assembled and merged with the drive train. The pump house finished in paint and had trim added. The body completed fabrication and began the paint process. Next week the cab and pump house should be merged with the chassis. The body should begin on the body line where harnessing and trim are added.

3/12/2016

Truck 1

This week your apparatus completed alignment and initial pump testing and had reflective striping applied. In the next few days your apparatus should complete 3rd party pump testing and be released to final product evaluation which is part of the quality process. This is your last scheduled report.

Truck 2

Early this week the cab finished on the cab line and was merged with the chassis along with the pump house. It also began the final assembly line where the body was merged with the chassis. In the next report, the tank should be added and the apparatus should continue on the final assembly line.

Truck 3

This week the cab finished on the cab line and has been merged with the chassis along with the pump house. The body finished in paint and completed the body line where harnessing and trim were added. Next week the chassis is scheduled to begin on the main assembly line where the body and water tank should be merged with the chassis.

Truck 4

This week the cab finished on the cab line and has been merged with the chassis along with the pump house. The body finished in paint and was on the body line where harnessing and trim are added. Next week the chassis is scheduled to begin on the main assembly line where the body and water tank should be merged with the chassis.

Truck 5

.This week the cab was nearing completion on the cab line while the chassis began assembly and had the drivetrain installed. The pump house and body finished in paint. In the next few days the chassis should be merged with the chassis. Next week the chassis should be merged with the pump house. The body may have harnessing and trim added.

Truck 6

This week the cab began on the cab line while the chassis began assembly and had the drivetrain installed. The pump house was painted while the body began the paint process. In the next few days the chassis should be merged with the chassis. Next week the chassis should be merged with the pump house. The body should finish in paint and may have harnessing and trim added.

Truck 7

This week the cab began on the cab line while the chassis began assembly and was ready to have the drivetrain installed. The pump house was painted while the body began the paint process. Next week the chassis is scheduled to be merged with the chassis and pump house. The body should finish in paint and may have harnessing and trim added.

Truck 8

This week the cab began on the cab line while the chassis began assembly. The pump house was painted while the body began the paint process in metal finishing. Next week the chassis is scheduled to be merged with the chassis and pump house. The body should finish in paint and may have harnessing and trim added.

Truck 9

This week the cab began on the cab line where cab related content is added while the chassis began assembly. The pump house was painted while the body panels were joined in fabrication. Next week the cab is is scheduled to be merged with the chassis and pump house. The body should begin the paint process.

Truck 10

This week the cab finished in paint. The pump house completed initial plumbing. The body began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added. The chassis may begin assembly. The pump house and body should begin the paint process.

3/5/2016

Truck 1
This week your apparatus finished on the main assembly line and was released to alignment and initial testing. Next week your apparatus is scheduled to finish initial testing and may be back on the line where reflective striping and/or remaining content is added.

\
 

Truck 2

This week the cab began on the cab line where cab related content is added while the chassis began assembly. The pump house was painted and was having flex tubing and trim added. The body was fabricated and began the paint process. Next week the cab is scheduled to be merged with the chassis and pump house. The body may have harnessing and trim added.

Truck 3

This week the cab began on the cab line where cab related content is added while the chassis began assembly. The pump house was painted. The body was fabricated and began the paint process in metal finishing. Next week the cab is scheduled to be merged with the chassis and pump house. The body should be nearing completion in paint.

Truck 4

This week the cab began on the cab line where cab related content is added while the chassis began assembly. The pump house was painted. The body was fabricated and began the paint process in metal finishing. Next week cab and chassis assembly should be nearing completion. The pump house may have trim added. The body should be nearing completion in paint.

Truck 5

This week the cab finished in paint. The pump house completed initial plumbing. Body panels were joined in fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may get painted. The body may begin the paint process.

Truck 6

This week the cab finished in paint. The pump house completed initial plumbing. Side body panels began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may get painted. The body panels should be joined in fabrication and the body may begin the paint process.

Truck 7

This week the cab was nearing completion in paint. The pump house completed initial plumbing. Side body panels began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may get painted. The body panels should be joined in fabrication and the body may begin the paint process.

Truck 8

This week the cab finished in paint. The pump house was fabricated and completed initial plumbing. Side body panels began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may get painted. The body panels should be joined in fabrication.

Truck 9

This week the cab was nearing completion in paint. The pump house began initial plumbing. Side body panels began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may move to paint. The body panels should be joined in fabrication.

Truck 10

This week your cab began the paint process. The pump house structure was fabricated while the pump had valves installed. Next week the cab should be nearing completion in paint. The pump should be installed in the pump house. The body is scheduled to begin fabrication.

 

2/27/2016

Truck 1
This week your apparatus was nearing completion on the main assembly line where a majority of the components have been installed. Next week your apparatus should finish on the main assembly line and is scheduled to be released to alignment and initial testing.

Truck 2

This week the cab finished in paint. Initial pump house plumbing was completed while side body panels began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may be painted. The body panels should be joined in fabrication.

Truck 3

This week the cab was nearing completion in paint. Initial pump house plumbing began. The body panels began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may be painted. The body panels should be joined in fabrication.

Truck 4

This week the cab was nearing completion in paint. Initial pump house plumbing began. The body panels began fabrication. Next week the cab is scheduled to begin on the cab line where cab related content is added while the chassis may begin assembly. The pump house may begin the paint process. The body panels should be joined in fabrication.

Truck 5

This week the cab continued in paint. The pump arrived and had valves installed while the pump house was fabricated. The body side panels began fabrication. Next week the cab should finish in paint. The pump should be installed in the pump house. Body panels should be joined in fabrication.

Truck 6

This week the cab began the paint process in metal finishing. The pump arrived and had valves installed. Next week the cab should finish in paint. The pump should be installed in the pump house. The body is scheduled to begin fabrication.

Truck 7

This week the cab began the paint process in metal finishing. The pump house structure began fabrication. Next week the cab should be nearing completion in paint. The pump should be installed in the pump house. The body is scheduled to begin fabrication.

Truck 8

This week the cab was fabricated and began the paint process in metal finishing. Next week the cab should continue through paint. The pump house and body are scheduled to begin fabrication.

Truck 9

This week the cab was fabricated and began the paint process in metal finishing. Next week the cab should continue through paint. The pump house and body are scheduled to begin fabrication.

Truck 10

This week the cab began fabrication. Next week your cab should begin the paint process in metal finishing.

 

2/20/2016

Truck 1
This week the body and water tank were merged with the chassis on the main assembly line where a majority of the components will be added. Next week your apparatus should be nearing completion on the main assembly line.

Click image for larger view

Truck 2

This week the cab began the paint process. Next week the cab should finish in paint. The pump house and body are scheduled to begin fabrication.

Truck 3

This week the cab was fabricated and began the paint process in metal finishing. Next week the cab should continue in paint. The pump house and body are scheduled to begin fabrication.

Truck 4

This week the cab was fabricated and began the paint process in metal finishing. Next week the cab should continue in paint. The pump house and body are scheduled to begin fabrication.

Truck 5

This week the cab was fabricated and began the paint process in metal finishing. Next week the cab should continue in paint. The pump house and body are scheduled to begin fabrication.

Truck 6

This week the cab began fabrication. Next week your cab should begin the paint process in metal finishing.

Truck 7

This week the cab began fabrication. Next week your cab should begin the paint process in metal finishing.